Substantial completion: from walkthrough to final payment

Substantial completion is the most important date on a job after the start date. It’s when the work is done enough for the owner to use it for what it was built for. It starts most warranties, usually releases most of the retainage, and moves responsibility for the building from the contractor to the owner. So it’s worth doing properly.

What the certificate records

On AIA jobs it’s the G704 Certificate of Substantial Completion. Whatever form you use, it should record:

The checklist

Before the walkthrough

At the walkthrough

After it

After closeout

Under AIA’s A201 general conditions, the contractor has a one-year correction period from substantial completion: work found not to meet the contract in that year has to be put right. It’s separate from, and doesn’t shorten, any longer warranties or the time the law allows for claims.

This is practical guidance, not legal advice. Your contract defines substantial completion and what follows from it.